Board approves courthouse change orders that add security upgrades and remove a railing requirement

May 19, 2026

The board approved change order #10 and related contract adjustments for the courthouse renovation, including a roughly $72,000 reduction tied to a removed railing obligation and an increase of just over $100,000 connected to security modifications such as FOB controls and delayed egress.

The full story

The Hall County Board approved change order #10 for the courthouse project, which included a cost reduction tied to eliminating a previously anticipated railing extension and an increase related to security upgrades.