District bond update: $95M committed, Three Springs foundation work progressing
Aug 25, 2026
District bond managers told the board the bond program is about $95 million committed so far; Three Springs micro‑pile and foundation work is complete in early areas, steel delays affected schedule but teams are pursuing a recovery plan.
The full story
District bond program managers told the board that bond spending and project work are largely on track following summer renovations, but they flagged near‑term procurement and schedule risks on larger projects. "We are currently right around 95 million committed," a program manager said, and staff noted that number will rise as remaining summer 2027 projects are bid and priced.