Construction update: DPS Station 30 and 31 progressing despite schedule adjustments
Aug 25, 2026
Chief Seery and contractor representative Marcus (AGCM) reported progress on DPS Station 30 and 31; Marcus said contractors added a 36‑day extension on one site and cited cumulative delays, but Station 31 is approaching enclosure and Station 30 is moving toward slab work.
The full story
Chief Seery introduced Marcus from AGCM for a construction update on two DPS stations. Marcus told the council that Station 30 incurred a contractor‑claimed time extension (36 days) and that cumulative delays related to select fill and moisture issues amounted to roughly 87 days; staff said they were working to tighten the schedule where possible.