Splash pad nearing completion; MDH testing and cameras next

May 7, 2026

Staff reported the splash pad is in final stages: replacement circuit boards arrived, Minnesota Department of Health testing is scheduled, eight cloud-based security cameras and bathroom fixtures remain to be installed before opening.

The full story

Staff provided a progress update on the new splash pad, reporting equipment replacements and pending regulatory testing. Michael said circuit boards that shorted out were replaced and MDH will test water clarity and filters this week; testing must be completed before staff install additional switches and finish electrical work.