Commission holds TriStar/Kramer payment after invoice mismatch; seeks missing breakdown

Sep 23, 2026

Commissioners paused a large contractor payment after staff could not reconcile a requested pay application amount with the balance-to-finish and retainage shown in supporting paperwork; they asked staff to obtain the missing explanatory page before releasing funds.

The full story

The commission put a contested contractor pay application on hold after staff identified a missing supporting page that explains why the contractor requested roughly $99,035.05 when other documents list a balance to finish and retainage totaling about $920,395.05.