Board hears semi-annual update on Phase II bond projects; Loveland Elementary demolition complete

Sep 8, 2026

Bond Oversight Committee chair and Project Advocates reported Phase II projects are on time and on budget; Loveland Elementary demolition and site grading are complete and the district has added scope beyond the original $121M, including security and performing-arts enhancements.

The full story

The Westside Community Schools Bond Oversight Committee presented its semi-annual Phase II update Sept. 8. Project Advocates' Matt Herzog and committee chair Ryan Decker told the board that completed Phase II projects met schedule and budget expectations and summer work advanced Westbrook building-envelope and HVAC upgrades.