Select Board approves electrical-panel replacement for Town Office HVAC work
Feb 9, 2026
Feb 9, 2026
The board authorized swapping the Town Office electrical panel after contractor estimates showed replacement was cheaper than tapping the transfer switch. A change order to air-seal and insulate the mechanical-room door was also noted and invoices presented.
The full story
Town staff told the Select Board that the Town Office HVAC renovation requires additional electrical work and a modest change order to complete the project. Jan Sotirakis presented two electrical options and associated costs and the board voted to replace the aging panel.