Supervisors approve secondary-roads pay request; local paving and culvert projects discussed
Jul 7, 2026
County roads staff updated supervisors on bridge replacements, box culvert installations and paving schedules; the board approved Turner Construction pay application for the Secondary Roads Addition & Garage.
The full story
County roads staff briefed the board on multiple north- and south-county projects: B Avenue and H Avenue bridge replacement work is progressing toward an estimated Sept. 1 completion, several box culvert installations are scheduled for August pending delivery, and paving work (including the F90 project) was delayed briefly because stormwater affected aggregate supply. Staff said many projects are near completion and that final deductive change orders are expected when punch-list items finish.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →