Architect warns Town Hall renovation will require safety upgrades or a variance
Apr 28, 2025
An architect presenting a MERP grant outlined that Goshen's Town Hall is a Type V-B building; without sprinklers the upstairs cannot be used as assembly space. The board discussed alternatives (alarm systems, rated exit access, occupancy limits) and agreed to pursue a variance request to the Division of Fire Safety.
The full story
An architect presenting on a MERP grant told the Select Board that Goshen’s Town Hall, classified as a Type V-B stick-frame building, faces life‑safety limits unless the project can provide sprinkler protection or accepted alternative measures.
"The first, you know, real big issue as indicated in the code review is this is a type 5 b building," the presenter said, explaining that such construction typically does not allow assembly occupancy on an upper floor without sprinklers. Because the town lacks municipal water and sewer, adding a sprinkler system would require substantial infrastructure work; the presenter said an alarm system and other fire‑protection measures were possible alternatives.
He listed retrofit items the Division of Fire Safety would expect: a fully addressable audible fire alarm (quoted by the presenter as roughly $30,000–$40,000), rated exit access and doors with closers, panic hardware if occupancy exceeds 50 people, removal or making inoperable the upstairs wood stove, illuminated exit signage, and guardrails. The presenter recommended submitting a variance/alternative compliance request to the regional manager at the Division of Fire Safety before completing construction drawings so the town can learn what package of measures would be acceptable.
Board members discussed design tweaks to reduce kitchen encroachment and noted that some exterior preservation goals (historic front room and stairs) could be preserved while directing accessibility and safety upgrades to an addition. The board agreed to have the presenter prepare marked-up plans and comparative options for the next meeting and to use MERP account funding to advance preliminary work.
Written with AI from the event video and transcript. Check it against the source ↓