Council weighs deductive change order to exit contractor JTL

Dec 10, 2025

Council members discussed options to end a construction contract with JTL, including a recommended deductive change order framed as lower risk than termination; staff noted JTL still must finish phase 1 and punch-list items with roughly $23,000 in retainage outstanding.

The full story

Matt opened the discussion of the town's contract with JTL, saying the council wants to "get out of this contract." He described a prior cancellation of a termination notice and urged clarity on remaining work and financial exposure.