County hires TSK for JLAC reprogramming, schematic design; $531,568 contract approved
May 7, 2026
The board approved a $531,568 contract with Kate Snyder Kimsey (TSK) to reprogram and produce schematic designs for renovation of the existing Judicial Law Enforcement Center (JLAC) in preparation for phased construction after occupants relocate to a new justice center.
The full story
The board approved a professional services contract with Kate Snyder Kimsey Architects (TSK) for $531,568 to reprogram and produce schematic-level renovation designs for the Judicial Law Enforcement Center (JLAC). Project manager Scott McCullough said TSK had previously conducted studies and is well positioned to update a 2015 space-needs assessment and produce schematics for phased construction on an estimated $15 million remodel budget.