Engineering updates: AMD projects, ROW progress and Chub Run bid moved to March 10
Feb 24, 2026
Feb 24, 2026
Engineers reported Phase 1 administrative items, Phase 2 has 30 of 34 ROWs secured with DOH permit under review, and the Chub Run vendor bid opening was postponed to March 10, 2026; Phase IV is awaiting contractor remobilization.
The full story
Town engineering staff provided a multi-part project update at the Feb. 24 meeting. For AMD Phase 1 they presented Change Order 4, Engineering Amendment 2 and a Notice of Acceptability. Phase 2 work has 30 of 34 required ROWs in hand; staff said they are still working to secure ROWs from two businesses, one utility and one resident, and that the Department of Health (DOH) permit is under review. A to-bid meeting with AML was scheduled for the following day.