Board approves $19.6 million guaranteed maximum price for new elementary school
Nov 17, 2025
Jackson Construction presented a Guaranteed Maximum Price of $19,603,856 for the district's new elementary school; asbestos abatement and commissioning add $235,000, bringing the total to $19,838,856. Trustees approved the GMP unanimously.
The full story
Bryan Parma, vice president of pre-construction for Jackson Construction, presented the Guaranteed Maximum Price (GMP) for the new elementary school included in the 2025 bond program, recommending a construction cost of $19,603,856. Parma told trustees the figure follows a review of bids from roughly 100 subcontractors and is intended as the maximum payable for the project as drawn.