Board approves $19.6 million guaranteed maximum price for new elementary school

Nov 17, 2025

Jackson Construction presented a Guaranteed Maximum Price of $19,603,856 for the district's new elementary school; asbestos abatement and commissioning add $235,000, bringing the total to $19,838,856. Trustees approved the GMP unanimously.

The full story

Bryan Parma, vice president of pre-construction for Jackson Construction, presented the Guaranteed Maximum Price (GMP) for the new elementary school included in the 2025 bond program, recommending a construction cost of $19,603,856. Parma told trustees the figure follows a review of bids from roughly 100 subcontractors and is intended as the maximum payable for the project as drawn.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in