Board hears building-program contingency update; $1.4M remains on $20M program
Jun 23, 2026
Board staff reported $1.4 million remaining in contingency funds for the district's $20 million building program, discussed delays at Hillham and contractor scheduling, and said the next contractor meeting is tomorrow.
The full story
Board staff gave the board an update on contingency spending for the district's building program, saying the district currently has about $1.4 million available from a total program budget of $20 million. The presenter said that total reflected a $14 million bond and $6 million drawn from fund balance.