Board hears building-program contingency update; $1.4M remains on $20M program
Jun 23, 2026
Jun 23, 2026
Board staff reported $1.4 million remaining in contingency funds for the district's $20 million building program, discussed delays at Hillham and contractor scheduling, and said the next contractor meeting is tomorrow.
The full story
Board staff gave the board an update on contingency spending for the district's building program, saying the district currently has about $1.4 million available from a total program budget of $20 million. The presenter said that total reflected a $14 million bond and $6 million drawn from fund balance.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or
Free account
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →