Chief Boo told the board the public safety building drywall contractor must increase liability insurance from $2 million to $4 million before county permitting proceeds; SROA permits are already in place and the district will pursue county permitting once insurance documentation is received.

The full story

Chief Boo briefed the board on the public safety building construction and drywall project, reporting that work cannot proceed to county permitting until the contractor's insurance coverage satisfies new requirements.

"Right now we're just waiting on Willow Creek Trevor to get his insurance stuff squared away. He had to increase his insurance liability from 2 million to 4 million," Chief Boo said. Once the contractor provides updated insurance documentation the district will file for county permits; the board noted SROA permitting is already complete on their side.

Board members discussed the county's faster permit turnaround when submissions are complete and the district emphasized it would not begin construction activity that lacked the required insurance and permits.