DDA tables $34,189 sidewalk change order amid easement, drainage and developer concerns

May 12, 2026

Staff presented Resolution 202651 for North Fraser sidewalk construction: design cost $4,679 and a contractor change order of $34,189. Board members questioned funding responsibility given unresolved easements with the Alvarez property owner and decided to table the sidewalk construction pending town negotiations and further information.

The full story

Staff presented Resolution 202651 to approve North Fraser AB sidewalk construction and explained that the construction change order totaled $34,189, chiefly due to drainage complications and right‑of‑way/easement issues. The original design work came in at $4,679.