Engineer reports progress on AMD phases, Chub Run and Phase IV; Nutter Run permitting noted complete
Aug 26, 2025
The town engineer updated the council on multiple projects: Phase 1 pay-application comments are being finalized for the September meeting; Phase 2 has 20 of 34 right-of-way parcels in hand and awaits OSM environmental clearance; Chub Run is on hold with a potential Oct. 1 start; Phase IV awaits DEP clearance for a forcemain; and Nutter Run permitting was listed as complete.
The full story
The town engineer provided a multi-item project update at the Aug. 26 meeting. For Phase 1 AMD, pay-application comments are being finalized and the engineer said the item "should be ready to be drawn down at September meeting." Phase 2 has 20 of 34 right-of-way (ROW) acquisitions in hand and is awaiting environmental assessment clearance from the Office of Surface Mining (OSM); the engineer said the project should be out to bid by the end of the year if clearances proceed.