Commissioners press for comprehensive‑plan timeline, worry about time and budget

Jan 2, 2026

Commissioners asked staff for a clear schedule on the county comprehensive plan, noting planner Josh is scheduled to meet with planning and zoning on the 8th and the 29th and expressing concern that the original contract amount was $150,000 with roughly $70,000–$80,000 spent so far.

The full story

Commissioner Bruce asked staff for an update on the comprehensive plan timeline and which topics have been completed. Staff said planner Josh is scheduled to meet with planning and zoning on the 8th and again on the 29th; commissioners clarified those are work‑group meetings and that the public hearing would be later in the process.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or