Commission sets direction on change-order approvals and reporting
Sep 23, 2026
Commissioners and staff discussed change-order practices for projects, favoring a percentage-based trigger (10%) with a $100,000 floor for commission review and monthly reporting on approved change orders to ensure oversight while allowing projects to continue.
The full story
Finance staff (S2) explained the draft change-order language distinguishing routine PO changes from project purchase-order changes: projects up to $60,000 and change orders up to 10% could be approved by the city manager, and larger or atypical overruns would be reported to the commission. Public-works participants (S6) argued for a percentage-based approach because dollar bands (for example, $60,000 to $600,000) can be a large jump and a 10% convention is commonly used in construction contingencies.