Drainage projects underway in River Ridge; crews working evenings and Saturdays
Jun 23, 2026
District engineers reported four drainage improvement sites are under construction with pipe and grading work; Palmetto Dunes requires removal and replacement of 12 trees, sod installation is planned the week of July 2, and the overall project is expected to finish by the end of July.
The full story
District Engineer Charlie Krebs told the Board that all four drainage-improvement sites are under construction, with sites cleared, silt fences installed and fill staged at Turnberry. "Mr. Krebs stated all four sites are under construction; sites are cleared and silt fences were installed," the transcript shows. Pipe work is scheduled in Oak Run the week of June 29 and sod is likely to be installed in Turnberry and Palmetto Dunes the week of July 2.