Council approves small increase for pond‑lining plan after vendor concerns
Feb 18, 2026
Staff recommended adding a drain‑tile system below the liner at Hole 4 to vent groundwater or gas; trucking and removal could raise costs by as much as $10,300, but staff said internal options may reduce that increase. Council authorized up to the additional $10,300, funded from golf CIP.
The full story
Jason Scharfencamp presented a change order to the Hole 4 pond‑lining project after the liner manufacturer raised concerns about subsurface gas and groundwater that could damage the liner. “One of their concerns was the integrity of the liner as well as any kind of gas or groundwater that may be under it,” Scharfencamp said, and he proposed installing a drain‑tile system to evacuate water or gas without damaging the liner.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →