Roadmaster: sewer work mostly complete, paving done on two roads; Swamp Bridge culvert delayed

Sep 25, 2026

Roadmaster Tom Showalter reported the sewer extension for Joy Christian Fellowship is complete except for paving; Forest Road and Yellow Mountain Road paving and line painting are complete but shoulders need backfill; Swamp Bridge Road culvert work is delayed with an estimated start around Sept. 13 and completion by Oct. 30.

The full story

Roadmaster Tom Showalter presented multiple operational updates at the Sept. 3 meeting. He said the sewer extension for Joy Christian Fellowship is complete except for paving, Forest Road and Yellow Mountain Road paving and line painting have been completed though the shoulders still need backfill, and shoulder mowing is finished.