County reports generator-project cost increases; staff seeks FEMA approval to reduce local share
Sep 9, 2026
Three of four county generator projects are complete but total project costs rose from about $385,000 to over $536,000; staff said FEMA review could lower the county share from $258,000 to roughly $75,000 if approved.
The full story
Amy updated the committee on four generator-installation projects that began under a grant. She said three of the four projects are complete but updated wiring, code compliance work and change orders pushed the total contract cost from an original estimate of about $385,000 to more than $536,000.