County inspector outlines MidAmerican pipeline permitting and oversight plan

Mar 11, 2026

Snyder & Associates project manager described MidAmerican's split docket and an expedited schedule seeking an operational date of Nov. 1; county will receive weekly reports and place two inspectors on site during construction, and will follow a tiered violation resolution process.

The full story

Christina Paradise, Snyder & Associates project manager and county‑contract inspector, told the board MidAmerican Energy has split its docket and filed for a waiver of a county public hearing to pursue an expedited schedule. "The goal the end goal is November 1, they wanna be operational," she said, explaining the company’s timeline and the county's inspection and reporting plans.