River Ridge CDD: drainage projects advance; tree removals and sod installation scheduled

Jun 23, 2026

District Engineer Charlie Krebs said drainage work at four sites is underway, pipes and grading are largely complete at Turnberry, and crews expect Palmetto Dunes to finish this week; twelve trees in Palmetto Dunes and six cabbage palms in Oak Run will be removed and replaced.

The full story

Charlie Krebs, District Engineer, told the Board that all four drainage sites are under construction, with sites cleared and silt fences installed. He said pipes had been installed and grading was completed in Turnberry, Palmetto Dunes is expected to be completed by the end of the week and pipe installation in Oak Run is scheduled for the week of June 29; if grading remains on schedule, the project is expected to be finished by the end of July.