Le Ray board approves developer agreement with National Grid for transmission-line work

Dec 11, 2025

The Town approved Resolution No. 17 (2025) accepting a Developer’s Agreement with Niagara Mohawk Power Corporation d/b/a National Grid for rebuilding a portion of a 15 kV transmission line; the company will submit a SWPPP for review and pay review fees.

The full story

At its Dec. 11 meeting the Town Board of Le Ray adopted Resolution No. 17 (2025) approving a Developer’s Agreement with Niagara Mohawk Power Corporation d/b/a National Grid for rebuilding part of the existing Black River–Coffeen 15 kV transmission line. The resolution notes that the project will require a Storm Water Pollution Prevention Plan (SWPPP) to be reviewed by the Town engineers and that review fees should be paid by the developer rather than town taxpayers.