County staff present roughly $41M plan for FLCC Spring Building; board asks for alternatives

Aug 10, 2026

County staff told supervisors the Spring Building schematic now carries a roughly $36M construction estimate and about $41M total project cost, and outlined funding options including a proposed $15M county bond, state match and donations. Board members asked staff to develop smaller-scope alternatives and confirmed a timeline for design and bidding.

The full story

County planning staff presented an updated schematic and funding plan for the proposed Spring Building on the FLCC campus, saying the construction estimate is about $35,750,000 (rounded to $36 million) and the full project scope pushes the total toward $41 million. Staff said the estimate reflects design progress, additional site work and an assumed escalation rate of about 8 percent.