Board approves time extension for county construction contract 24-R002
Jan 7, 2025
Jan 7, 2025
Las Animas County approved Change Order #5, a time extension for contract 24-R002 (A&S, now United Construction). The board noted paperwork delays and voted unanimously to approve the extension.
The full story
Administrator Phil Dorenkamp told the board that contractor A&S—now operating as United Construction—had requested a time extension for contract 24-R002 and that the paperwork had been delayed pending authorization from the contractor's main office. He asked that the county not penalize the firm because the request was received before the deadline.