Engineer: Ione wastewater project substantially complete; punch list remains

Aug 11, 2026

Anderson Perry & Associates reported the city’s wastewater project reached substantial completion July 31, 2026; the contractor is addressing a punch list with final payment due Aug. 30 and AFP No. 22 under review. Consultant budget items and a warranty-bond arrangement were outlined.

The full story

Bill Ledbetter, engineer with Anderson Perry & Associates, updated the council on the city wastewater project on Aug. 11, reporting that a Substantial Completion walkthrough was held July 27 and the project was found substantially complete. He said the contractor was addressing punchlist items and, as of Aug. 10, estimated about a week of work remained to finish those items.