Council weighs options as Springvale Park bids come in over budget

Sep 25, 2026

Bids for the Springvale Park improvements came in above the FY27 construction budget. Staff reported $446,000 available for construction while the lowest base bid was $519,500; council signaled support for the base scope with a half pavilion and resurfacing/parking if funding or sponsorships materialize.

The full story

City staff told the council the Springvale Park improvement project — proposed to add a walking track, restroom, a dog park and resurfacing of the parking lot — is partially funded but that construction bids exceeded the available funds. "The FY 27 budget allocated $500,000 for the project," the city manager said, and after engineering there is "approximately $446,000 available for construction." The lowest base bid came in at "$519,500," leaving a shortfall under the base scope.