Project manager reports partial pay requests and a $66,001.76 change order
Jul 14, 2026
Jul 14, 2026
Project manager Steve Datchy told the board partial pay request #8 (~$159,000) and #9 ($537,000) have been submitted, described installation of mains and testing, and said change order #2 totaling $66,001.76 covers a 15‑inch stub and additional electrical/stormwater work; completion may require a schedule extension to October.
The full story
Project manager Steve Datchy updated the board on construction finance and schedule.
