City Engineer John Choinka told the board that McBride's escrow for Boone Ridge Manor cannot be released until January 2026 per the agreement and that McBride is responsible for concrete repairs in Elkhorn Ridge and will handle plowing until repairs are made.

The full story

City Engineer John Choinka updated the board on subdivision and infrastructure matters in Elkhorn Ridge and Boone Ridge Manor. Choinka told the Bord that McBride's escrow for Boone Ridge Manor "would not be eligible for release until January of 2026 after inspections" because the agreement began in January 2025; he also reported that McBride's portion of Elkhorn Ridge was marked up in early spring and required concrete replacement and repairs.