Site changes, permitting timeline outlined for 101 Green Lane project

Aug 5, 2022

Presenters said Building B will be moved to meet city code, sidewalks and fencing will be added, a site review was submitted on 08/01 with an expected 4–8 week review, and building-permit submissions would follow ahead of an August 2023 construction start.

The full story

Presenters described concrete design changes for the 101 Green Lane project intended to meet city requirements and preserve existing on-site trees and drainage.