Engineer briefs council on water-plant change order; revised pricing requested

Aug 4, 2026

Jones Petrovinski engineer Josh Wyman described change order #8 to add duplicate chemical-feed systems for the water treatment plant; an initial contractor quote of $103,633.69 would draw heavily on contingency, and Wyman said he expects revised pricing by midweek for council review.

The full story

Joshua Wyman, consulting engineer with Jones Petrovinski, presented change order #8 for the town's water-treatment plant project, describing additional chemical-feed systems and associated piping, pumps and valves that would let the plant run two treatment trains independently. "Our initial quote that we got from the contractor was, a $103,633.69," Wyman said, adding that one subcontractor's pricing was higher than expected and that the team had met on-site to refine scope.