Engineers propose one‑block addition to phase‑1 project; council approves amendment and feasibility study
Feb 24, 2025
DGR Engineering told the council phase 1 of the sewer/storm project has about $800,000 in unused grant‑eligible capacity; council approved a $94,500 engineering amendment (resolution 2025‑03) to design and observe an extra block on 2nd Avenue and authorized a feasibility study and hearing to add five properties to the assessment role.
The full story
Trent Bruce of DGR Engineering briefed the council on phase‑1 of the sewer and storm project and recommended adding a block of work on 2nd Avenue so the city can use remaining grant funds rather than returning them.