Staff urge coordination with PMs when estimating TA completion and construction start dates

Jul 15, 2026

Attendees asked for guidance on estimating TA completion and construction start dates; presenters said early estimates are uncertain, require coordination with assigned PMs, and are tied to construction funding timing.

The full story

Attendees asked whether the meeting minutes form provides guidance for estimating TA completion dates and construction start dates. James said that early in a project there is inevitable uncertainty and that teams should "coordinate with the assigned technical assistance PM to kind of land on a reasonable date," adding that construction start estimates are heavily dependent on construction funding timing.