Board approves contingency modification for Guthrie High wrestling facility construction
Sep 15, 2026
Board approved contingency modification No. 3 for Crossland Construction to add previously omitted roof curbs for the Guthrie High wrestling facility; staff said the work was omitted because some drawings were not complete when the metal building bid was issued and the project remains within contingency.
The full story
The board considered and approved contingency modification No. 3 for Crossland Construction to add roof‑curb work to the Guthrie High School wrestling facility contract after staff explained the curbs were not included in the original bid package because certain drawings were incomplete at bid time.