4 Mile Road project timeline pushed as Wisconsin Gas and Caledonia sequencing changes work plan

Sep 12, 2025

Public works reported Wisconsin Gas will relocate mains and Caledonia will televise and replace sanitary sewer sections; the sequencing delays Wind Point's water/main restoration and will require trenching and phased traffic/repair decisions, extending project timing into next year.

The full story

Public works staff updated the board on 4 Mile Road: Wisconsin Gas unexpectedly notified the village it will begin gas relocation work, which in turn delayed the planned sanitary television and replacement work by Caledonia and pushed Wind Point’s water main restoration later in the construction sequence. The village anticipates directional boring for much of the gas work, but the sanitary and laterals work will require trenches across the roadway in sections and replacement of roughly 51 laterals in the project area.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in