Director reports November chiller delivery, generator contractor issues and RFP results

Sep 22, 2026

In his operational report, the facilities director said the airport chiller is expected in November, noted problems with a Cummins-related contractor on generator controls, reported the jail UPS bid closes Oct. 6 and said Excel Engineering ranked highly among RFP respondents for a relocation/design project.

The full story

In the director's operational report, Mike said the new airport chiller is expected in November and that staff will follow up with shipping-date updates. "The airport chiller, the new chiller is expected in November," he said when summarizing near-term project timelines.