Engineer: Aransas County drainage study about 60–70% complete; 24 projects targeted for master plan

Sep 29, 2026

Pape Dawson Engineering told the county Sept. 28 that a countywide stormwater study is roughly 60–70% finished and has narrowed an initial list of damage centers toward 24 proposed master‑plan projects; staff will model top candidates for funding under the Water Development Board’s programs.

The full story

Jake Powell of Pape Dawson Engineering told the court the countywide drainage study has reduced about 64 initial ‘damage centers’ to roughly 42 projects for further analysis and that the team aims to deliver a master plan with about 24 projects by summer 2027. “Overall, we’re probably 60 to 70% done,” Powell said, adding the next steps are detailed modeling, cost‑benefit analyses and preparing abridged applications for state flood‑management funding.

Powell described the committee’s scoring system (0–100) that weighs life‑safety risk to structures, ingress/egress impacts, habitat and complexity across jurisdictions; the highest score on the current cut was 62. He identified six projects the team will model immediately — Magnolia Street/Austin Street pump upsizes, Mesquite–Chaparral/7th Street, Market/Liberty streets and two Holiday East/7th Street groupings — and said the county will not need to allocate money now to add projects to the regional list. County staff and commissioners asked about coordination with neighboring San Patricio County and TxDOT; Powell said the team will share models and said TxDOT staff have toured local sites but have not committed funding.

Written with AI from the event video and transcript. Check it against the source ↓