CDD approves $1.11 million drainage improvement contract with Clark Construction
Apr 28, 2026
Apr 28, 2026
The River Ridge CDD board voted unanimously to award Clark Construction a not-to-exceed $1,111,860 contract for four stormwater phases after adding a 5% contingency to cover unknown costs, bringing the project total from $1,058,914.45 to $1,111,860.
The full story
The River Ridge Community Development District on April 28 approved a not-to-exceed $1,111,860 contract with The Clark Construction Group, Inc. for drainage improvements covering Oak Run, Turnberry, Palmetto Dunes and Seaside IV. The board voted unanimously on a motion by Mr. Blumenthal and a second by Mr. Mountford to accept Clark's bid and add a supplemental 5% contingency to the contractor's pricing.