MRGCD reports successful directional drill: new siphon pulled under Rio Grande

Sep 24, 2026

MRGCD told the council it completed a directionally drilled HDPE siphon under the Rio Grande — about 1,200 feet long and 80 feet deep at the pinch point — and expects the remaining construction to be finished around Dec. 31; inspectors will use camera inspections and a planned O&M schedule.

The full story

Representatives from the Middle Rio Grande Conservancy District updated the council on construction of a new siphon beneath the Rio Grande that will restore reliable water delivery across a key crossing. The presenters said contractors successfully pulled a continuous plastic (HDPE) pipe under the river after redesigning the initial casing and that the pull itself took roughly one working day (about seven hours).