Atkinson council approves $329,059 payment and substantial completion for water main project
Oct 7, 2024
Oct 7, 2024
Council approved Payment Application #1 of $329,059 (including a deductive change order of $88,341) and issued a Certificate of Substantial Completion for Atkinson Water Main Improvement Project #463-C1-003.
The full story
At its Oct. 7 meeting the Atkinson City Council approved Payment Application #1 for $329,059.00 for the Atkinson Water Main Improvement Project; the payment package includes Change Order #1, a deductive adjustment in quantities totaling $88,341.00. The motion was moved by Helen Olson, seconded by Chuck Asher, and passed by roll call.