Wheat Ridge approves $1.58M settlement with contractor over Wadsworth delays

Sep 29, 2026

Council approved a settlement agreement with Concrete Works of Colorado Inc. for $1,581,982 to resolve CenturyLink-related utility relocation delay claims on the Improved Wadsworth project; payment to be made from capital improvement funds.

The full story

The Wheat Ridge City Council approved a settlement with Concrete Works of Colorado Inc. totaling $1,581,982 to resolve claims tied to CenturyLink utility relocation delays on the Improved Wadsworth project.

City staff said the contractor had earlier been granted 43 additional working days for the delay and subsequently requested $4,260,000 in additional compensation, including an electrical subcontractor claim. After mediation and a dispute-review board recommendation, the parties accepted the recommended settlement amount; staff said capital-improvement-program funds are available to pay the settlement and that payment would be due within 10 days of council approval.

Councilor Dan Larson said he supported the settlement motion but expressed disappointment the city did not pursue litigation, noting the financial impact on capital projects. The motion to approve the settlement passed unanimously.

Written with AI from the event video and transcript. Check it against the source ↓