Commission finalizes application checklist and mapping radius for Article 30

Oct 1, 2026

The planning commission reorganized submittal requirements (site plan, narrative, utility verifications, noise model, road-use approvals, waste-stream and decommissioning plans) and extended the project map radius to 1 mile for public-notice clarity.

The full story

Commissioners reorganized the application checklist for conditional use permits related to data centers. The list will require a narrative describing facility capacity and water/electric needs, a site plan drawn to scale, a map of the project area showing residences and institutions within 1 mile, utility verifications, preconstruction sound modeling, road‑use approvals, an emergency response plan, a waste-stream management plan and a decommissioning plan.