Developer to relocate access and interconnect; ComEd connection remains pending

Oct 2, 2026

The approved amendment moves the site's access road per the township road commissioner's request and shifts the interconnection point west; the developer said final pole or line work will be determined by ComEd and could involve off‑site line extensions paid for by the project but owned by ComEd.

The full story

The amendment the zoning board approved authorizes the developer to move the project's access from Greenwood to a point about 700 feet west, per a request from the township road commissioner. The change prompted board questions about interconnection and whether additional off‑site poles or easements along Vandercar Road would be required.