Council members were told Streetscape concrete work is largely complete between 14th and 15th Streets, bricklaying will begin on 15th Street, plaza conduit work is underway and a DMX lighting representative will be on site Sept. 7 to set lighting patterns.

The full story

Monaca Borough Manager David L. Kramer, Jr. told council the Streetscape project has advanced to 14th Street and that most of the concrete between 14th and 15th Streets is finished. He said bricklaying will begin on 15th Street and that lighting and benches will be installed after that work is complete.