Westchester reports progress on water-main, sewer lining and street program

May 13, 2025

Public Works staff told the board that emergency and planned water-main work has advanced across multiple streets, with Windsor Drive emergency main completed, the 2025 water-main project under way from Wedgewood to Roosevelt, and sewer lining and street restoration scheduled as part of the 2025 program.

The full story

Public Works staff gave a detailed update at the May 13 board meeting on multiple infrastructure projects under way in Westchester. The Windsor Drive emergency water main has been installed and John Erie Construction is finishing asphalt patches and parkway restoration. The 2025 water-main project started May 1; staff reported that the main line has been completed from Wedgewood to Roosevelt and planned service transfers will take about a month before the old main can be taken out of commission.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in