Cheney construction update: kitchen expansions advance, Craig Road Elementary foundation permitted
Apr 15, 2026
District construction staff and contractors told the board that kitchen expansions at Salina and Windsor are on schedule, switch-gear and lighting upgrades are planned for summer 2026, and the new Craig Road Elementary has received a foundation permit with GARCO targeting substantial completion July 22, 2026.
The full story
District construction and bond-program contractors gave the board a progress briefing on multiple projects funded by the district bond program. Lisa, a representative from Yuri, said work is proceeding on kitchen expansions at Salina Elementary (demo and footings complete) and that Windsor’s kitchen is scheduled to start in June; temporary power and switch-gear work are staged for summer 2026.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →